道达尔位于安哥拉Zinia二期项目开始投产

道达尔位于安哥拉Zinia二期项目开始投产
2021年05月07日 09:07 中国石化新闻网

原标题:道达尔位于安哥拉Zinia二期项目开始投产

  中国石化新闻网讯 据OE网站5月6日报道,法国石油巨头道达尔已开始从安哥拉近海的Zinia二期项目生产石油,该项目与现有的Pazflor FPSO相连。

  Zinia二期项目包括9口井的钻探,预计到2022年年中日产量将达到4万桶。

  Zinia二期项目位于距安哥拉海岸约150公里、水深600 - 1200米的海域处,其石油储量约为6500万桶。

  道达尔称,该项目的开发按计划进行,资本支出比预算低10%以上,节省了1.5亿美元。其涉及300多万工时的工作,其中200万工时是在安哥拉完成的,没有发生任何事故。

  道达尔非洲勘探和生产总裁Nicolas Terraz表示,尽管疫情带来了挑战,但该项目的成功启动表明道达尔致力于确保17号区块的可持续产量,该区块的生产许可证最近延长至2045年。Zinia二期项目反映了安哥拉投资回报率高的短周期项目的质量。

  安哥拉国家石油、天然气和生物燃料局(National Oil,Gas and Biofuels Agency)首席执行官保利诺·杰罗尼莫(Paulino Jeronimo)评论道,Zinia二期项目是安哥拉的一个重要项目,在适当的时候到来,以维持该国的生产。我们欢迎道达尔公司与我们在安哥拉的合作,该公司不断与其合作伙伴投资开发该国的石油资源。

  道达尔作为17号区块运营商,持有38%的股份,另外合作伙伴有Equinor(22.16%)、埃克森美孚(19%)、BP勘探安哥拉有限公司(15.84%)和Sonangol P&P(5%)。该集团在该区块的主要生产区运营四艘浮式生产储油船,即Girassol、Dalia、Pazflor和CLOV。

  郝芬 译自 OE

  原文如下:

  Total Brings Online Zinia Phase 2 Offshore Angola

  French oil major Total has started oil production from the Zinia Phase 2 project offshore Angola, connected to the existing Pazflor FPSO.

  The Zinia Phase 2 project includes the drilling of nine wells and is expected to reach a production of 40,000 barrels of oil per day by mid-2022.

  Located in water depths from 600 to 1,200 meters and about 150 kilometers from the Angolan coast, Zinia Phase 2 resources are estimated at 65 million barrels of oil.

  "The development of this project was carried out according to schedule and for a CAPEX more than 10% below budget, representing a saving of 150 million dollars. It involved more than 3 million manhours of work, of which 2 million were performed in Angola, without any incident," Total said.

  "The successful start-up of this project, despite the challenges that have arisen as a result of the pandemic, demonstrates Total’s commitment to ensure a sustainable output on Block 17, for which the production license was recently extended until 2045. Zinia Phase 2 project reflects the quality of short-cycle projects in Angola with high return on investment”, said Nicolas Terraz, President Africa, Exploration and Production at Total.

  Paulino Jeronimo, CEO of the National Oil, Gas and Biofuels Agency, commented as follows, “Zinia Phase 2 is a key project for Angola that comes at the right time to sustain the production of the country. We welcome our collaboration with Total in Angola, that keeps investing with its partners in the development of the country oil resources”.

  Block 17 is operated by Total with a 38% stake, alongside with Equinor (22.16%), ExxonMobil (19%), BP Exploration Angola Ltd (15.84%) and Sonangol P&P (5%). The group operates four FPSOs in the main production areas of the block, namely Girassol, Dalia, Pazflor and CLOV.

海量资讯、精准解读,尽在新浪财经APP
道达尔 投产

APP专享直播

1/10

热门推荐

收起
新浪财经公众号
新浪财经公众号

24小时滚动播报最新的财经资讯和视频,更多粉丝福利扫描二维码关注(sinafinance)

7X24小时

  • 05-10 创益通 300991 13.06
  • 05-10 浙江新能 600032 3.51
  • 05-10 诺泰生物 688076 15.57
  • 05-07 康拓医疗 688314 17.34
  • 05-07 电气风电 688660 5.44
  • 股市直播

    • 图文直播间
    • 视频直播间
    新浪首页 语音播报 相关新闻 返回顶部